Finance committee OKs $64M extra spending on new Ottawa central library – Ottawa

Ottawa’s finance and financial improvement committee agreed to cowl its share of the inflated prices tied to the brand new central library facility at its assembly Tuesday morning, with a groundbreaking now anticipated within the weeks forward.
Councillors first learned last week that the prices associated to the brand new joint facility with Library and Archives Canada had jumped considerably attributable to hovering development business prices tied to the COVID-19 pandemic.
Initially pegged at a price of $192.9 million, the grand complete for the venture will now are available round $334 million, per the lowest-cost bid from PCL Development.
Ottawa’s share of the price will now be $168 million, or $64 million greater than initially budgeted in 2018 when the venture was first permitted.
The finance committee permitted the additional spending with a unanimous vote Tuesday morning. The worth hike nonetheless wants sign-off from the Ottawa Public Library Board at its assembly later within the day on Tuesday and at metropolis council’s subsequent assembly on Oct. 27.
The library board itself would cowl roughly $12 million in further prices in improvement cost debt and an additional $16 million from its reserves, that are sitting comparatively flush after two years of surpluses, the committee heard Tuesday.
There can be roughly $3 million left within the library reserves after the withdrawal, in response to the town’s chief monetary officer Wendy Stephanson.
Town would cowl the remainder of the funding by means of taking up further debt.
Stephanson informed the finance committee the town is ready to get preferential charges on the debt by extending its time period to 40 years from the initially deliberate 20 years.

A lot of the brand new debt will substitute debt presently on the town’s books that’s set to mature within the coming years, she added.
An additional $10 million wanted for a 200-spot underground parking storage may even be coated off by debt however can be paid again by parking price revenues from the ability.
Employees additionally managed to search out some financial savings within the venture itself largely by downsizing a number of the deliberate areas and swapping supplies the place potential, however councillors had been promised that the design the general public has been proven is basically the identical because the deliberate finish product.
Ottawa’s new library additionally “compares favourably” on a price per sq. foot foundation with different central libraries in Canada, Stephanson mentioned.
Selecting to not go forward with the brand new library at this stage would imply a sequence of monetary problems and spurned companions within the venture.
For one, PCL’s low-cost bid would expire on Nov. 8, so delaying previous that time would imply beginning the procurement course of over once more and, in all chance, paying extra for the ultimate product as bids are revised primarily based on ongoing inflation.
Substantial delays would even be a difficulty for the present central department location on Metcalfe Avenue. Ottawa bought that constructing and is leasing the area from the brand new proprietor, however that deal is ready to run out in 2026 — the identical yr the brand new library facility is now anticipated to open.
Ottawa’s planning normal supervisor Stephen Willis mentioned Tuesday that the town does have a clause in its settlement to increase that time period ought to the brand new library face additional delays, however the rental charges can be increased than what the town is paying now.
Town has additionally signed agreements with LAC to develop their new shared residence collectively; terminating that partnership would put the town in murky authorized waters, employees mentioned.
Canada’s chief archivist Leslie Weir informed the committee that LAC’s present residence on Wellington Avenue is slated to be taken over by different authorities stakeholders within the years to return, so any additional problems to this venture would go away the library within the lurch.
“It might be fairly devastating for us,” she mentioned.
Pumping the brakes on the brand new library may additionally damage the town’s relationship with the First Nations of Kitigan Zibi and Pikwakanagan, who’ve partnered with the planning group to form the design and different components of the library from early within the course of.
Ādisōke, the title for the library, borrows the Anishinābemowin phrase for “storytelling” and was unveiled at a ceremony with First Nations companions earlier this yr.
Chatting with the finance committee Tuesday morning, Kitigan Zibi director of training Anita Tenasco held up the brand new library as “a chance for us to work on reconciliation.”
“This is a chance for us to collaborate in such a robust, significant manner. We definitely hope that the funding might be discovered for this facility,” she mentioned.
Ought to the funding plans be confirmed by the library board and metropolis council within the week forward, the contract is predicted to be awarded to PCL by Nov. 8. A groundbreaking would occur on the website earlier than the tip of the autumn.